BCG: flexible grid connections could cut AI data‑centre power wait to 2–4 years

Why it matters for readers: It explains one practical way to reduce long waits for electricity as AI data‑centre demand grows.

  • BCG finds flexible access can lower time to power from 5–10 years to 2–4 years by reducing need for major grid reinforcement.1
  • Using on‑site power generation and storage alongside flexible connections can let data centres become operational earlier and ease pressure on electricity grids.1
  • The report's analysis focuses on five Northwest European markets — the UK, Germany, France, Belgium and the Netherlands — for the 2030–2035 investment period.1
  • BCG projects global data‑centre power demand will reach around 210 gigawatts by 2030, up from about 84 gigawatts in 2025.1